These production numbers are based on metered daily production, and may thus differ slightly from the final production volumes that will be used for accounting purposes due to changes in stock volumes etc.
Further increases in production are limited by the temporary facility which is now at capacity (1,200 boepd nameplate/design capacity). New, permanent facilities with an initial capacity of around 3,000 boepd is scheduled to be operational by December 19, and further production will be phased in as current wells are opened further and new wells are drilled.
Oslo, 4.12.2007
Rocksource ASA
Trygve Pedersen
CEO
+ 47 90 09 77 41
Published: 04.12.2007